Abstract
Relying on the Beijing-Zhangjiakou high-speed railway Cao Mao Shan tunnel project, blasting vibration monitoring and sound wave testing experiments were carried out. The monitoring results show that the blasting vibration velocity corresponding to the initial support satisfies the Sadowski formula. The results of the sonic test show that with the increase of blasting times, the cumulative damage increases gradually, but the blasting damage increment shows a downward trend. In addition, as the blasting distance decreases, the blasting cumulative damage effect is significant. Through data analysis and curve fitting, the cumulative damage range Rcr and critical blasting vibration velocity PPVcr corresponding to blasting construction are obtained respectively. The numerical analysis results show that there is a good exponential function relationship between the cumulative damage range Rcr and the corresponding critical blasting vibration velocity PPVcr. The purpose of quantitative control of blasting damage can be achieved by setting the corresponding vibration velocity threshold.
Similar content being viewed by others
Introduction
Blasting construction has the advantages of simple operation, good economic benefits and fast construction progress, so it is widely used in transportation infrastructure, municipal engineering and metal mining. For tunnel projects, especially mountain tunnel projects, blasting construction technology1,2,3 is still the main method for excavation and advancement. In general highway and railway tunnel projects, the composite support system consisting of anchor spraying support and integral cast-in-place concrete is the main form of lining structure. The chemical energy released instantly during blasting not only breaks the rock mass, but also diffuses to the surrounding area in the form of stress waves4,5,6,7,8. The tunnel lining structure, especially the initial support close to the blast source, is greatly affected by the blasting vibration. In addition, under the action of multiple blasting vibration loads, microscopic damage or even macroscopic cracking will inevitably occur inside the initial support concrete of the tunnel, weakening its structural bearing capacity9,10,11. Therefore, it is necessary to conduct a systematic study on the cumulative damage effect of the initial support of the tunnel under the action of cyclic blasting dynamic loads.
In the past 30 years, many scholars12,13,14 have introduced the concept of damage variables based on the knowledge of continuum damage mechanics and formed a series of theoretical models of blasting cumulative damage through mathematical statistics or numerical simulation. D.E.Crady et al.15 believed that the number of newly generated cracks under blasting obeys the exponential distribution law. Based on indoor model experiments, L.M.Taylor et al.16 established the functional relationship between damage variables and elastic modulus and crack distribution density. T. Kawmaoto et al.17 considered engineering rock mass as a continuous material with original defects and believed that there is a close relationship between the macroscopic defects and microscopic damage of the rock mass. In other words, the damage variable is an important intermediate link between the macroscopic defects and microscopic damage of the engineering rock mass. A.M.Rubin et al.18 found that the longitudinal wave velocity inside the rock mass is related to the degree of development of its internal cracks, and the degree of blasting damage to the rock mass can be evaluated by the change in the longitudinal wave velocity inside the rock mass. In addition, the K-G model, TCK model and Yang-Liu model are also widely used in the study of rock damage.
The above studies are centered on the damage of surrounding rocks under blasting dynamic loads, but there are few studies on the damage effects of tunnel lining structures, especially on the initial support. Based on a large indoor model experiment, Shan et al.19 discussed the destructive effect of tunnel blasting on freshly shotcrete by using the acoustic wave testing method. Based on the results of ultrasonic testing, Zhu et al.20 studied the cumulative damage effect of secondary lining concrete under multiple blasting and established a functional relationship between the cumulative blasting damage and the number of blasting cycles. From the perspective of blasting stress wave transmission, Chen et al.21 studied the contribution of blasting stress P wave and S wave to lining concrete damage. The above studies on the damage characteristics of lining concrete were all obtained through acoustic wave testing. However, due to the influence of the acquisition environment during on-site monitoring, acoustic wave testing often encounters certain operational difficulties. Compared with sonic wave testing, blasting vibration monitoring is simple and easy, and it is less affected by the environment. Therefore, many relevant specifications or studies22,23,24 used the critical particle peak velocity of blasting damage corresponding to engineering rock mass as the safety criterion for cumulative damage of rock mass blasting, and have achieved good application results. As shown in Table 1, Bauer and Calder25 divided the PPV thresholds of different rock mass blasting damage according to the degree of rock mass damage.
Mojitabai and Beattie26 defined the critical value of PPV for engineering rock mass based on the mineral composition of the rock, as shown in Table 2.
Based on the Damaoshan Tunnel project, Xia et al.27 systematically studied the damage effect of blasting in a newly built tunnel on the lining structure of the adjacent existing tunnel, and proposed a blasting damage control method based on PPV. Cao et al.28 used LS-DYNA to study the cumulative damage effect of cutting blasting on interlayers in parallel tunnels and established a mathematical relationship between the maximum segment charge, damage range and critical PPV. For blasting excavation projects on rock slopes, Yang et al.29 investigated the development of blasting damage variables along the slope surface through acoustic wave testing and numerical simulation. Due to the influence of explosion shock waves and flying rocks, it is not realistic to arrange blasting vibration monitoring instruments at the critical damage boundary. Therefore, Yang set the PPV-related threshold of the upper slope to achieve the purpose of controlling slope damage. In the Guangdong Aoling Nuclear Power Plant Phase II foundation blasting excavation project, Xia et al.30 studied the intrinsic relationship between the transmission of blasting vibration waves and foundation blasting damage variables by combining on-site acoustic wave testing with FLAC3D simulation. Field engineering practice shows that the PPV of the rock mass 30 m away from the explosion source can be used as the only indicator to control the blasting damage range of the nuclear power plant foundation. Xia et al.31 conducted a special case study on blasting damage of columnar jointed basalt at the Baihetan dam site. The results showed that the PPV critical threshold can be considered as an inherent property of the engineering rock mass and is not affected by the blasting construction method or the detonation method. So, similar to the treatment method for rock mass, can the same treatment idea be used for the study of blasting damage in the initial support of tunnels? This is a question worth thinking about and studying.
Relying on the Caomaoshan Tunnel Project of Beijing-Zhangjiakou High-Speed Railway, this paper mainly studies the blasting vibration effect and cumulative damage characteristics of the initial support concrete under tunnel blasting construction condition. By introducing the concept of cumulative damage variables, the functional relationship between the critical distance of blasting damage and the corresponding PPV threshold is studied, in order to achieve the purpose of quantitatively controlling the cumulative damage range of initial support blasting.
Project background and monitoring plan
Project background
The Beijing-Zhangjiakou high-speed railway starts from Beijing North Station, with stations such as Qinghe, Badaling Great Wall, Xiahuayuan, Xuanhua North, etc. along the way, and ends at Zhangjiakou Station. The railway is 174 km long and is one of the important channels connecting Beijing with Shanxi and Inner Mongolia. Caomaoshan Tunnel32 is a key control project of the Beijing-Zhangjiakou High-speed Railway, located in Chenjiazhuang Village, Xuanhua District, Zhangjiakou City, Hebei Province. The new tunnel adopts a single-hole double-track mode with a total length of 7,340 m. The tunnel passes through the main vein of Caomaoshan, with a maximum burial depth of about 109 m. The tunnel passes through the new loess and silty clay strata of the Upper Pleistocene of the Quaternary System. The fully weathered tuff it passes through has moderate expansion, which may cause accidents such as water inrush, mud inrush, surrounding rock collapse and large deformation, posing a major safety hazard to the blasting construction in this area of the tunnel. The tunnel entrance section is mainly composed of Grade III surrounding rock. Figure 1 is the layout of the Caomaoshan Tunnel entrance work area.
Site layout of the tunnel entrance area33.
According to the tunnel surrounding rock grade and geological conditions, the tunnel entrance section is excavated mainly using the step method, and the amount of explosives used in the blasting construction process is strictly controlled. The blasting excavation depth is controlled within the range of 2.0 m ~ 3.0 m. The blasting construction uses 2# rock emulsion explosive, the diameter of the blast hole is 42 mm, and the diameter of the charge roll is 32 mm. Tunnel blasting uses an axially uncoupled spacing method to install explosives and electronic detonators for detonation. The length of the gun mud filling is not less than 0.3 m. A large amount of explosives is used for blasting on the upper steps of the tunnel, which causes greater blasting vibration. The arrangement of blastholes on the upper steps of the tunnel is shown in Fig. 2, and the specific charge amount and blasting construction parameters are shown in Table 3.
According to the on-site construction plan, the initial support of the tunnel is mainly an anchor-sprayed structure consisting of shotcrete combined with wire mesh, locking anchor rods, etc. During the on-site construction process, steel plates are used to reinforce the locking anchor rods and form a “U”-shaped connection with the steel frame. In addition, the thickness of the shotcrete is 12 cm. The length of the anchor inserted into the rock mass is 4.5 m and the diameter is 32 mm.
On-site monitoring test plan
The on-site test content mainly includes two main parts: blasting vibration monitoring and blasting sound wave testing. The blasting vibration monitoring uses the TC-4850 blasting vibration meter developed by Zhongke Measurement and Control Co., Ltd. The blasting vibration meter is equipped with three specific channels, which can simultaneously collect the blasting vibration speed and vibration frequency in three mutually perpendicular directions. The blasting sound wave test uses the RSM-SY5 intelligent sound wave detector developed by the Wuhan Institute of Rock and Soil Mechanics, Chinese Academy of Sciences. Considering the content of this test, the acoustic wave test was carried out using the flat measurement method, that is, the test transducer was arranged on the surface of the initial support of the tunnel. As shown in Fig. 3, a total of 6 measuring points were arranged in this field test. During the first blasting construction, measuring point 1 was 10 m away from the tunnel face, and the adjacent spacing of other measuring points was 10 m. As the tunnel section is excavated, the distance between the monitoring point and the explosion source changes accordingly. During the on-site monitoring process, the blasting vibration sensor is fixed to the initial support surface of the tunnel through the configured stainless steel clips, so that each sensor is close to the outer surface of the tunnel lining. In addition, each vibration sensor is 2.5 m away from the bottom of the tunnel. Before the experiment, a homemade steel cage was placed outside the vibration meter to prevent it from being damaged by rocks thrown during the blasting process. During the field test, the sensor’s X direction was toward the tunnel face, the Y direction was toward the inside of the tunnel diameter, and the Z direction was perpendicular to the XY plane and upward.
To reduce the test error, acoustic wave tests were carried out at 0.1 m on both sides of the vibration sensor, and the straight-line distance between the two horizontal transducers was 0.2 m. In the experiment, butter was used as a transducer coupling agent to keep the transducer close to the wall surface to improve the test effect. After each blasting construction, three parallel ultrasonic tests are carried out, and the average value of the three test results is used as monitoring result. The specific on-site arrangement of blasting vibration monitoring and acoustic wave testing is shown in Fig. 4.
Based on the above description, the monitoring points corresponding to the blasting vibration monitoring and the acoustic wave test are located at the same position. In other words, the R corresponding to the blasting vibration measurement point and the acoustic wave measurement point is approximately equal. As the tunneling progresses, the distances from the explosion corresponding to the vibration measuring points and the sound wave measuring points also change. During on-site monitoring, the laser rangefinder can be used to measure the distance from the explosion corresponding to each blasting operation, which facilitates subsequent analysis and calculation.
Field test data analysis
Analysis of blasting vibration monitoring data
As shown in Fig. 5, compared with the PPV in the three directions in the blasting vibration time history curve, the blasting vibration velocity corresponding to the vertical direction is the largest. According to the requirements of relevant specifications34,35,36,37,38, this paper conducts subsequent research on the PPV corresponding to the vertical direction.
A total of 6 blasting vibration field monitoring tests were conducted from October 12 to October 21, 2018. Since the surrounding rock grade corresponding to the blasting construction of this section of the tunnel remained basically unchanged, the maximum charge per delay used in the blasting construction was 39.3 ~ 43.2 kg. At present, the Sadovsky formula is often used to reflect the attenuation law of blasting vibration, and the specific expression can be expressed as:
where PPV represents the peak particle velocity, Q represents maximum charge per delay, R represents the distance between the measuring point and the blasting source, and K and α represent the geological parameters and attenuation parameters related to the blasting vibration transmission, respectively.
Based on the field measured data, according to formula (1), regression fitting is performed and the fitting results are shown in Fig. 6. The specific fitting equation is expressed as follows:
As shown in Fig. 6, the determination coefficient (r2) corresponding to formula (2) is 0.980, with high fitting accuracy, which can accurately reflect the blasting vibration attenuation law of the initial support concrete of the tunnel.
Analysis of blasting sound wave test results
Considering the composition of concrete, primary cracks will exist on the surface of cement mortar, the interface between mortar and aggregate, and the surface of aggregate. Under the action of blasting vibration, the initial support concrete will first produce stress concentration at the tips of these cracks and cause local damage. As the number of blasting times increases, the number of microcracks gradually increases, and finally expands into macrocracks, resulting in a significant reduction in the bearing capacity of the concrete. At this point, if further damage effects occur, the concrete will suddenly break and fail.
In the process of blasting damage research, the cumulative damage variable Di is often used to represent the degree of damage.
where Em0 represents the elastic modulus of the rock mass before the initial support concrete blasting, and Emi represents the elastic modulus of the rock mass after the i-th blasting.
The Technical Specification for Excavation of Rock Foundations of Hydraulic Structures (SI47-2020) (2020) stipulates that the corresponding longitudinal wave velocity change rate before and after blasting should be used as the basis for evaluation.
where ηi represents the rate of change of the longitudinal wave velocity of the rock mass before and after blasting construction, Cpi represents the longitudinal wave velocity of the rock mass corresponding to the i-th blasting, and Cp0 represents the longitudinal wave velocity of the rock mass corresponding to the blasting.
According to the elastic mechanics hypothesis, there is a certain functional relationship between the elastic modulus of rock mass and its longitudinal wave velocity. There is the following mathematical relationship between the blasting damage variable Di and the rate of change of the longitudinal wave velocity ηi.
where Di represents the cumulative damage variable corresponding to the i-th blasting.
According to the “Technical Specifications for Construction of Rock Foundation Excavation Engineering of Hydraulic Structures” (SI47-2020), when η < 0.1, the rock mass is considered to be undamaged or slightly damaged; when 0.1 < η ≤ 0.15, the rock mass is considered to be slightly damaged; when η > 0.15, the rock mass is considered to be damaged or the excavated rock mass is of poor quality. That is, η = 0.1 can be used as the control threshold, and the corresponding critical value of rock mass cumulative damage Dcr = 0.19.
Before blasting construction, three acoustic wave tests were carried out near each vibration measuring point to obtain the corresponding longitudinal wave velocity, and the average value of the three test results was taken as Cp0. Within 24 h after each blasting construction, the longitudinal wave velocity of the corresponding initial support concrete is measured at the same position, and the corresponding longitudinal wave velocity Cpi after each blasting can be obtained, i = 1,2…,6. The results of the acoustic wave test are shown in Table 4.
Based on the data in Table 4, the cumulative damage Di is obtained through formulas (3 ~ 5) as shown in Table 5. It can be seen from Table 5 that as the number of blasting increases, the blasting cumulative damage variables corresponding to each measuring point gradually increase. In addition, the closer the measuring point is to the blasting source, the greater the cumulative damage. After six blasting experiments, the cumulative damage corresponding to measuring point 1 is as high as 0.331, which has exceeded the critical damage threshold of 0.19. In addition, the cumulative damage (D) corresponding to measuring points 2, 3, and 4 also exceeds the control threshold. However, it can be found that with the increase in the number of blasting times, the damage increment tends to gradually decrease, which shows that the damage effect induced by blasting vibration does not cause sudden fracture and damage of the initial supporting concrete.
In order to more clearly analyze the changes in blasting damage variables, the relationship between the cumulative damage variable Di corresponding to each blasting construction and the number of blasting times is plotted in Fig. 7. As shown in Fig. 7, the cumulative damage variable and the number of blasting times are approximately monotonous linear. As the blasting distance increases, the corresponding fitting straight line slope decreases from 0.029 to 0.0063, and the change rate of the damage variable shows a gradually decreasing trend. Taking Dcr=0.19 as the criterion, it can be found that as the number of blasting increases, the cumulative damage variables corresponding to multiple measuring points exceed 0.19. Among them, measuring point 1 is the shortest distance from the blasting source, and the cumulative damage variable corresponding to the second blasting has exceeded 0.19, which is significantly affected by the blasting vibration damage.
Cumulative damage characteristics of initial support concrete
The analysis results in Sect. "Field test data analysis" show that the damage effect of the initial support of the tunnel is significant under the blasting load. However, the impact scope of blasting damage and specific control standards are not clearly defined. Therefore, this section systematically studies the cumulative damage characteristics of initial support through theoretical analysis methods, in order to obtain the threshold standard suitable for tunnel blasting damage control. First, the R-D scatter plots corresponding to each blasting test are drawn based on the data in Table 5. Among them, I~VI represent the first to sixth blasting tests respectively. As shown in Fig. 8, the cumulative damage variable D corresponding to the six blasting tests and the blasting distance R all show a good polynomial function relationship. We obtained six blasting tests using Dcr = 0.19 as the criterion, and the damage ranges Rcr corresponding to the initial support were 10.11 m, 25.38 m, 42.38 m, 52.50 m, 62.57 m and 73.02 m respectively. It can be seen that with the increase in the number of blasting times, the blasting damage range corresponding to the initial support of the tunnel gradually increases. This phenomenon is caused by the influence of the cumulative damage caused by blasting.
Since the charge used in the blasting construction of this section of the tunnel remains basically unchanged, the PPV can be expressed as a function of the blasting distance. Through the curve fitting method, the relationship between PPV and R is obtained as follows:
Figure 9 shows that the determination coefficient (r2) corresponding to formula (6) is 0.907, and the fitting accuracy is relatively high. Through the Rcr obtained by the above calculation, we can get the PPVcr corresponding to the critical damage position is 26.55 cm/s, 12.14 cm/s, 7.85 cm/s, 6.54 cm/s, 5.63 cm/s and 4.94 cm/s respectively.
A large number of research results39,40,41 show that the critical blasting damage distance is an important engineering parameter in blasting engineering and directly affects the calculation of blasting damage range. Currently, the critical blasting damage distance of tunnel rock mass or initial support is mostly obtained by using acoustic wave testing or numerical simulation. However, acoustic wave testing is significantly affected by the on-site testing environment, and the monitoring work is difficult, so the monitoring effect is not easy to guarantee. The accuracy of numerical simulation results depends on the on-site test results and the selection of geotechnical engineering parameters. The calculation is time-consuming and not easy to be used by engineering practitioners. Relevant engineering practice and research42,43,44 show that under the influence of blasting power, the critical damage distance (Rcr) and the critical damage particle peak velocity (PPVcr) show a good nonlinear relationship. Compared with the sonic wave test, the blasting vibration test is simple and easy to perform.
Therefore, it is worthwhile to explore in depth whether the damage range of the initial support of the tunnel can be controlled by controlling the value of the critical damage particle peak velocity (PPVcr). Therefore, the correlation data of critical damage distance (Rcr) and critical damage particle peak velocity (PPVcr) are plotted as a scatter plot as shown in Fig. 10. The data fitting results in Fig. 10 show that there is a good exponential function relationship between PPVcr and Rcr, with a determination coefficient as high as 0.997. From the above analysis, it can be seen that, for this tunnel project, the purpose of quantitatively controlling the scope of blasting damage of the initial support of the tunnel can be achieved by setting the corresponding blasting vibration velocity threshold range.
For example, if the actual project requires that the blasting cumulative damage range of the initial support of the tunnel should not exceed 50 m, then it can be calculated that Rcr = 50 m corresponds to PPVcr = 5.72 cm/s. That is, when the PPV is less than or equal to 5.72 cm/s, the initial support damage range of the tunnel caused by cyclic blasting is less than or equal to 50 m.
Conclusion
Relying on the Caomaoshan Tunnel Project of Beijing-Zhangjiakou High-Speed Railway, blasting vibration monitoring and acoustic wave testing were carried out. This paper obtained the blasting vibration attenuation law of the initial support of the tunnel and the distribution characteristics of the blasting cumulative damage. Through data fitting, the article organically combines blasting vibration and cumulative damage, hoping to achieve the purpose of quantitatively controlling the scope of blasting damage in the initial support of the tunnel by setting the corresponding blasting vibration velocity threshold.
-
(1)
As the number of blasting increases, the cumulative damage of the initial support of the tunnel increases. As the blasting distance increases, the increment of the cumulative damage shows a trend of gradually decreasing, and the corresponding fitting line slope of the blasting cumulative damage decreases from 0.029 to 0.0063.
-
(2)
Taking Dcr=0.19 as the control standard, the blasting cumulative damage ranges (Rcr) corresponding to each blasting test were 10.11 m, 25.38 m, 42.38 m, 52.50 m, 62.57 m and 73.02 m respectively. Combined with the attenuation law of blasting vibration, the critical vibration velocities (PPVcr) of blasting damage are obtained to be 26.55 cm/s, 12.14 cm/s, 7.85 cm/s, 6.54 cm/s, 5.63 cm/s and 4.94 cm/s respectively.
-
(3)
The numerical analysis results show that there is a good exponential function relationship between the blasting damage range (Rcr) and the corresponding blasting damage critical vibration velocity (PPVcr). In the early stage when the surrounding rock grade, rock mass lithology and blasting footage remain basically unchanged, the purpose of quantitatively controlling the cumulative damage range of the initial support blasting of the tunnel can be achieved by setting the corresponding blasting vibration velocity control threshold.
Data availability
If necessary, the raw data in the manuscript can be obtained by contacting the first author or corresponding author.
Abbreviations
- PPV :
-
Peak particle velocity
- σ c :
-
Uniaxial compressive strength
- R :
-
Distance from the blast area
- Q :
-
Maximum charge per delay
- R cr :
-
Distance corresponding to critical damage
- PPV cr :
-
Peak particle velocity corresponding to critical damage
- D :
-
Cumulative damage
References
Ainalis, D., Kaufmann, O., Tshibangu, J. P., Verlinden, O. & Kouroussis, G. Modelling the source of blasting for the numerical simulation of blast-induced ground vibrations: A review. Rock. Mech. Rock. Eng. 50, 171–193. https://doi.org/10.1007/s00603-016-1101-2 (2017).
Ji, L., Zhou, C., Lu, S., Jiang, N. & Gutierrez, M. Numerical studies on the cumulative damage effects and safety criterion of a large cross-section tunnel Induced by single and multiple full-scale blasting. Rock. Mech. Rock. Eng. 54, 6393–6411. https://doi.org/10.1007/s00603-021-02630-9 (2021).
Yang, C., Zhou, K., Gao, R. & Xiong, X. Numerical investigation of the dynamic response of a preconditioned roof in an underground mine: A case study of mining environment regeneration. Soil. Dyn. Earthq. Eng. 140, 106457. https://doi.org/10.1016/j.soildyn.2020.106457 (2021).
Li, L. et al. Energy spectrum analysis of blast waves based on an improved Hilbert-Huang transform. Shock Waves 27, 487–494. https://doi.org/10.1007/s00193-016-0667-7 (2017).
Hu, Y. G., Yang, Z. W., Huang, S. L., Lu, W. B. & Zhao, G. A new safety control method of blasting excavation in high rock slope with joints. Rock. Mech. Rock. Eng. 53, 3015–3029. https://doi.org/10.1007/s00603-020-02113-3 (2020).
Huo, X. F. et al. Rock damage control for large-diameter-hole lateral blasting excavation based on charge structure optimization. Tunn. Undergr. Sp Tech. 106. https://doi.org/10.1016/j.tust.2020.103569 (2020).
Lu, W. B., Leng, Z. D., Hu, H. R., Chen, M. & Wang, G. H. Experimental and numerical investigation of the effect of blast-generated free surfaces on blasting vibration. Eur. J. Environ. Civ. En. 22, 1374–1398. https://doi.org/10.1080/19648189.2016.1262285 (2018).
Zhang, Z. G. & Qiu, W. G. Study on the impact zoning of the construction project of the adjacent building construction of the subway section tunnel. Mod. Tunn. Technol. 53 (1), 75–82 (2016).
Zhao, Y., Shan, R. L., Wang, H. L. & Xin, B. Y. Vibration response and evaluation system of cross-tunnel blasting. B Eng. Geol. Environ. 81 https://doi.org/10.1007/s10064-022-02911-9 (2022).
Zhou, Z., Gao, W. Y., Liu, Z. Z. & Zhang, C. C. Influence zone division and risk assessment of underwater tunnel adjacent constructions. Math. Probl. Eng. 2019 https://doi.org/10.1155/2019/1269064 (2019).
Wang, H. et al. Safety evaluation and application of blasting vibration based on an improved Hilbert–Huang transform. Rock. Mech. Rock. Eng. 56, 3971–3991. https://doi.org/10.1007/s00603-023-03272-9 (2023).
Zhang, Z. et al. Dynamic response and safety control of civil air defense tunnel under excavation blasting of subway tunnel. Tunn. Undergr. Sp Tech. 112, 103879. https://doi.org/10.1016/j.tust.2021.103879 (2021).
Wang, X., LI, J., Zhao, X. & Liang, Y. Propagation characteristics and prediction of blast-induced vibration on closely spaced rock tunnels. Tunn. Undergr. Sp. Tech. 123, 104416. https://doi.org/10.1016/j.tust.2022.104416 (2022).
Duan, B., Xia, H. & Yang, X. Impacts of bench blasting vibration on the stability of the surrounding rock masses of roadways. Tunn. Undergr. Sp. Tech. 71, 605–622. https://doi.org/10.1016/j.tust.2017.10.012 (2018).
Grady, D. E. & Kipp, M. E. Continum modeling of explosive fracture in oil shale. Int. J. Rock Mech. Min. Sci. 17 (3), 147–157. https://doi.org/10.1016/0148-9062(80)91361-3 (1980).
Taylor, L. M., Chen, E. P. & Kuszmaul, J. S. Microcrack-induced damage accumulation in brittle rock under dynamic loading. Comput. Methods Appl. Mech. Eng. 55, 301–320 (1986).
Kawamoto, T., Ichikawa, Y. & Kyoya, T. Deformation and fracturing behavior of discontinuous rock mass and damage mechanics theory. Int. J. Numer. Anal. Met. 12, 1–30. https://doi.org/10.1002/nag.1610120102 (1988).
Ahrens, T. J. & Rubin, A. M. Impact-induced tensional failure in rock. J. Geophys. Res. Planet. 98, 1185–1203 (1993).
Shan, Y. L., Huang, B. & Geng, H. H. Model experiment on cumulative damage effect of fresh shotcrete under blasting dynamic load. Blast Shock 36 (03), 289–296 (2016).
Zhu, H. B., Yang, X. L. & Ye, H. Y. Experimental study on accumulation law of blasting damage of tunnel lining concrete. Railway J. 40 (03), 132–136 (2018).
Chen, M. & Lu, W. B. Research on the propagation effect of P wave on cracks in mass concrete. Geomechanics 2007(01), 123–126 .https://doi.org/10.16285/j.rsm.2007.01.024
Xia, J., Wang, B., Guo, X. & Xie, Z. Vibration response and safety control for blasting vibration of the existing tunnel with defects. Undergr. Space 15, 76–89. https://doi.org/10.1016/j.undsp.2023.08.011 (2024).
Xie, L. X. et al. Damage evolution mechanisms of rock in deep tunnels induced by cut blasting. Tunn. Undergr. Sp. Tech. 58, 257–270. https://doi.org/10.1016/j.tust.2016.06.004 (2016).
Esen, S., Onederra, I. & Bilgin, H. A. Modelling the size of the crushed zone around a blasthole. Int. J. Rock. Mech. Min. 40, 485–495. https://doi.org/10.1016/S1365-1609(03)00018-2 (2003).
Bauer, A. & Calder, P. N. .Open pit and blast seminar. Course No.63221, 1978. Mining Engineering Depa Rtment, Queens University, King ston, Onta rio, Canada.
Mojitabai, N. & Beatti, S. G. Empirical approach to prediction of damage in bench blasting. Trans. Inst. Min. Metall. Sect. A 105, A75–A80 (1996).
Xia, X., Li, H. B., Li, J. C., Liu, B. & Yu, C. A case study on rock damage prediction and control method for underground tunnels subjected to adjacent excavation blasting. Tunn. Undergr. Sp. Tech. 35, 1–7. https://doi.org/10.1016/j.tust.2012.11.010 (2013).
Cao, F., Ling, T. H., Li, J. & Hang, F. Analysis of cumulative damage characteristics of interlayer rock in small clearance tunnel under cyclic blasting load vibration and shock. 37(23), 141–148. (2018).
Yang, J. H., Cai, J. Y., Yao, C., Zhang, X. B. & Liu, L. S. Discussion on blasting vibration monitoring for rock damage control in rock slope excavation. Earthq. Eng. Eng. Vib. 21, 53–65. https://doi.org/10.1007/s11803-021-2071-2 (2022).
Xia, X., Li, H. B. & Zhang, D. Y. Control standards for bedrock blasting at Hongyanhe nuclear power plant. Explos. Shock Wave 30 (01), 27–32 (2010).
Xia, W. J., Lu, W. B. & Chen, M. Study on the safety threshold of peak vibration velocity of blasting damaged particles in columnar jointed basalt at Baihetan dam site. Chin. J. Rock Mech. Eng. 38 (S1), 2997–3007 (2019).
Zhao, Y., Shan, R., Wang, H., Tong, X. & Li, Y. Regression analysis of the blasting vibration effect in cross tunnels. Arab. J. Geosci. 14 https://doi.org/10.1007/s12517-021-08257-y (2021).
Zhao, Y., Shan, R. L. & Wang, H. L. Research on vibration effect of tunnel blasting based on an improved Hilbert–Huang transform. Environ. Earth Sci. 80 https://doi.org/10.1007/s12665-021-09506-9 (2021).
Indian Standard Institute. Criteria for Safety and Design of Structures Subjected to Underground Blast. ISI Bull IS-6922. (1973).
Siskind, D. E., Stagg, M. S., Kopp, J. W. & Dowding, C. H. Structure response and damage produced by ground vibrations from surface blasting. Report of Investigations 8507, U.S. Bureau of Mines, Washington DC; (1980).
China Standards Association. Safety regulations for blasting. GB6722-2014. (2014).
Deutsches Institut fu¨r Normung (DIN). Vibrations on building construction, Part 3-Effects on structures. DIN 4150-3, Berlin. (1986).
Guan, X. M., Zhang, L., Wang, Y. W., Fu, H. X. & An, J. Y. Velocity and stress response and damage mechanism of three types pipelines subjected to highway tunnel blasting vibration. Eng. Fail. Anal. 118 https://doi.org/10.1016/j.engfailanal.2020.104840 (2020).
Li, H. B. et al. Rock damage control in bedrock blasting excavation for a nuclear power plant. Int. J. Rock. Mech. Min. 48, 210–218 (2011).
Shan, R. L. et al. Research on the zoning of blasting for ultra-deep hole cylindrical charges based on thick-walled cylinder theory. Mech. Adv. Mater. Struct. https://doi.org/10.1080/15376494.2024.2320808 (2024).
Zhao, Y., Shan, R. L. & Wang, H. L. Blasting vibration effect and safety evaluation method of railway cross tunnels. Tunn. Undergr. Sp. Tech. 145 https://doi.org/10.1016/j.tust.2024.105588 (2024).
Zeng, Y. Q. et al. Research on blasting vibration effect and time-frequency characteristics of vibration signals in a road corridor at xianning nuclear power station. J. VibroEng. 23, 823–846. https://doi.org/10.21595/jve.2021.21848 (2021).
Zeng, Y. Q. et al. Blast-induced rock damage control in Fangchenggang nuclear power station, China. J. Rock Mech. Geotech. Eng. 10, 914–923. https://doi.org/10.1016/j.jrmge.2018.04.010 (2018).
Qin, H. F., Zhao, Y., Wang, H. L., Ge, L. J. & Tong, X. Damage prediction and improvement method based on cutting mode of circular empty hole. Sci. Rep. -UK 14 https://doi.org/10.1038/s41598-024-61599-x (2024).
Acknowledgements
The work described in this paper was supported by the National Natural Science Foundation of China (51878242, 52274148), the Hebei Institute of Architecture and Engineering Doctoral Initiation Fund (B-202304), scientific research project of colleges and universities in Hebei Province (BJK2024118) and Basic Research Projects of Shijiazhuang Universities in Hebei Province (241790797 A, 241790877 A).
Author information
Authors and Affiliations
Contributions
Yan Zhao is responsible for methods, Zhuang Zhang is responsible for numerical analysis, Lingling Xu is responsible for formal review, Lijie Ge and Huadong Zhao are responsible for initial draft review, and Mingzan Yu is responsible for supervision.
Corresponding author
Ethics declarations
Competing interests
The authors declare no competing interests.
Additional information
Publisher’s note
Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations.
Rights and permissions
Open Access This article is licensed under a Creative Commons Attribution 4.0 International License, which permits use, sharing, adaptation, distribution and reproduction in any medium or format, as long as you give appropriate credit to the original author(s) and the source, provide a link to the Creative Commons licence, and indicate if changes were made. The images or other third party material in this article are included in the article’s Creative Commons licence, unless indicated otherwise in a credit line to the material. If material is not included in the article’s Creative Commons licence and your intended use is not permitted by statutory regulation or exceeds the permitted use, you will need to obtain permission directly from the copyright holder. To view a copy of this licence, visit http://creativecommons.org/licenses/by/4.0/.
About this article
Cite this article
Zhao, Y., Zhang, Z., Ge, L. et al. Cumulative damage characteristics of tunnel initial support concrete under blasting load. Sci Rep 15, 2975 (2025). https://doi.org/10.1038/s41598-024-84032-9
Received:
Accepted:
Published:
DOI: https://doi.org/10.1038/s41598-024-84032-9